
The trim dozer, a Liebherr 712 with GPS receivers on the blade, shaping the wetland at Breakout Creek.
THE legion of navvies who
dug out Breakout Creek in the
1930s would surely be
impressed with how it looks
today. Back then, flooding
along the lower reach of the
Torrens River regularly inun
dated as far inland as where
Adelaide Airport is today.
Breakout Creek, designed to
cope with a 1-in-200 year
flood, diverts the river out to
sea at Henley Beach South.
The area became urban as
houses were built; the creek
was fenced off and used for the
agistment of horses and little
else.
In the 1990s, the Torrens
Catchment Water Management
Board now part of the Adelaide
and Mount Lofty Ranges
Natural Resources Manage
ment Board, came up with a
staged wetlands project for 1.2
km of the river. In 1999, 500m
upstream from Henley Beach
Road at Lockleys was made
into a demonstration wetland at
a cost of $550,000. Bulk earth
works for the remaining
700m/10ha between Henley
Beach and Tapleys Hill roads
were completed in July, having
taken three months. The
existing waterway was
widened and deepened so that
two channels of open water
flow around submerged islands
of reeds (to be planted). At the
time of writing (winter 2009),
40,000 out-of-water plants had
been planted; in spring, 20,000
water plants will go in.
Connell Wagner, now part of
the Aurecon Group, won the
design, documentation and
superintendency contract; and
BMD e*3 won the construction
contract. Greening Australia
was tasked to grow all the
plants, and is subcontracted by
BMD to plant and maintain
them for two years. Excluding
tsemi tipper drivers, a peak
workforce of 24 cut 60,000m3
of material; half was reused on
site while the rest was reused
off-site as it was excess to the
design.

The wetland looking upstream towards Henley Beach Road just prior to the planting of 40,000 out-of-water plants.
Equipment included four 7t
to 33t excavators, two bobcats,
12 semi tippers, “an incredibly
manoeuvrable” 25t articulated
dump truck a GPS-controlled
small dozer (to trim to level)
and two 12t rollers. An 8” (20
cm) stationary pump and a
variety of smaller pumps were
used to control water levels.
Project manager Sam Phillips
says “the whole timing of
wetland projects is to complete
the earthworks in time to plant
the plants at the right time of
the year. The bulk earthworks
and one of the two concrete
weirs were completed when
one of the big rains started. It
was beautiful timing.”
A week was lost when
Torrens Lake weir malfunc
tioned on the night of February
11 and “let go” a slug of water
flowing up to 1.5m deep
through the site. A big rain
event cost another week.
Phillips says the horse fences
have come down, the horses
are further downstream and
there’s a network of paths
down to the water similar to the
first stage.
“What was there before was
not a biodiverse environment.
We have removed more than 30
weed species,” he says. The
new wetland will have grassed
areas and viewing platforms,
and a boardwalk crossing will
connect the east and west
banks. Like stage one, it will
have permanent water and
increase the habitat for native
fish (arriving via a fish ladder
at Henley Beach South), frogs
and water birds. Expect koalas,
too, as one was seen recently in
the stage one area. Phillips
expects the 1.6 km section
from Tapleys Hill Road to the
sea (now an agistment area) to
become a wetland at some time
in the future.